Installation guide
Put your yurt up yourself.
Every UK Yurt is designed to be installed with common hand tools. Follow the steps below, watch the videos, and take it at your own pace. If you would rather we did it, we can quote for installation and commissioning on site.
The build, in order
Six steps from base to weather-tight.
The riveted lattice and steel tension mean no specialist rigging. Work through the steps in order and do not skip the tension checks.
- 01
Prepare your base
Mark out a level platform to the footprint for your diameter. A timber deck maximises lifespan, but hard-standing or well-drained ground works too. We will send you the exact base dimensions for your configuration.
- 02
Lay the floor and door frame
Stand the door frame on the base line and lay the floor panels around it. Check it is square and level before anything else goes up, as everything references off this frame.
- 03
Raise the ash lattice
Unfold the riveted ash lattice wall in a ring around the floor, lift it upright and clip the top ends to the crown. Two people make this quick; the riveted joints mean no re-tying of khana.
- 04
Tension the roof
Lift the crown, insert the ash roof ribs evenly, then bring up the galvanised steel tension cable. Tension the cable in stages so the roof settles into a true circle.
- 05
Fit the covers
Pull the wall canvas over the lattice, then the welded PVC roof cover over the ribs and crown. Secure the tension band and dress the cover so it sits evenly all round.
- 06
Seal and finish
Fit the door, windows and any flue outlet. Check the tension band is even, the door swings true and the roof is taut. Your yurt is now weather-tight and ready to use.
Videos
Watch before you start.
Raising the frame
How two people stand the ash lattice and crown in under an hour.
Tensioning the roof cable
Staged tensioning so the roof settles into a true circle.
Fitting the welded PVC cover
Pulling, dressing and sealing the roof cover in any weather.
Video walkthroughs are sent with your build. The full library is available to customers after ordering.
On the day
Tips from the workshop.
- Allow a full day for a first-time two-person install; a team of three is faster.
- Keep the steel tension cable and roof ribs numbered so they go back in the same order.
- Fit the flue outlet before the roof cover is dressed, so the seal is set properly.
- Re-tension the cable after the first week of standing, then seasonally.
- Do not over-tension the wall band, the structure is designed to flex in the wind.
Prefer a fitted install?
We can put it up for you and sign it off on site.
Build your configuration and we will quote for delivery, installation and commissioning so the yurt is tensioned and weather-tight before we leave.